Fitted across two school holidays without closing a single classroom. 420 pupils now read last week’s output aloud in Monday assembly.
on the installed cost, paid from the district’s capital fund. The bill savings stay in the school’s own budget.
Figures from the lobby screen’s monitoring feed and two years of utility statements, checked with Theo Lindqvist in September 2026.
The district wanted panels on the hall and both classroom wings, but would not close a classroom for it. Theo Lindqvist gave us two windows: Easter and the summer break.
Panels craned onto the classroom wings over the Easter break; the hall roof, inverters and lobby screen in the summer holiday. Pupils never shared the site with a crew.