§1 Site sheetSR-214 / Sample figures

Sector | Food and drink, snack food producer |
Scope | 2 sites, 6 lines, 412 devices |
Findings | 2 High, 9 Low |
Windows | 7 used, all signed |
Result | Vendor access now timed and logged |
Written for the plant manager: what we found on the floor, how the work ran, and what is different now.
Two sites, six lines, three shifts a day. The asset list was a spreadsheet from the last expansion, and four machine vendors dialled in with their own remote tools whenever a line faulted.
A sensor went on a mirror port at each site, with no outage. Four weeks of listening gave a list of 412 devices. Every change after that went into one of seven windows, each signed by the plant manager.
Vendors now reach their machines through one gateway, for a set time, under their own names, and every session is logged. In 14 months no line has stopped because of our work.
§3 FindingsSR-214 / Sample figures

High | 2 | |
Low | 9 | |
Windows used | 7 |
Severity | Finding | Status |
High | Four vendor remote tools, always on, with no log | Closed in W4 |
High | One flat network from the office to the line PCs | Closed in W2 |
Low | PLC firmware three versions behind | Held for shutdown |
Low | Shared login on the packing line HMIs | Closed in W3 |
§4 Window logSR-214 / Sample figures
Copied from the site log. Every window had a date, a rollback and a signature before it opened.
When | Work | Signed by | Line |
Week 1 | Sensors on mirror ports at both sites | Controls lead | No outage |
Weeks 1 to 4 | Listen and build the asset list, 412 devices | Wardline | No outage |
Week 5 | Asset list and findings walked through on site | Plant manager | No outage |
W1 | Plant DMZ firewall rules, site 1 | Plant manager | Signed window |
W2 | Plant DMZ firewall rules, site 2 | Plant manager | Signed window |
W3 | Vendor gateway in, first vendor moved | Plant manager | Signed window |
W4 | Other three vendors moved to the gateway | Plant manager | Signed window |
W5 | Line 2 switch firmware, restart witnessed | Plant manager | Signed window |
W6 | Line 5 switch firmware, restart witnessed | Plant manager | Signed window |
W7 | Old remote tools removed from line PCs | Plant manager | Signed window |
Afterwards | |||
Month 2 | First monthly monitoring report | Wardline | Monthly |
Month 14 | Still no stop caused by our work | Plant manager | 0 stops |
§5 Plant noteSR-214 / Sample figures
I expected a list of reasons to shut down. I got a map of my plant and a plan that fit the schedule I already had.
One vendor gateway, timed and logged
Office and lines split by a plant DMZ
An asset list that updates itself