Writing a rollback plan your night shift can follow

Two engineers at a factory control console with a window onto the plant floor

A rollback plan is read at the worst moment, by someone who did not write it. If it needs the engineer who made the change, it is not a plan.

We write every rollback for the operator on the night shift. One page, printed, and taped inside the cabinet door for the length of the window.

What goes on the page

  1. The one sign that tells you to roll back, in words the operator already uses.
  2. The steps, in the order the hands move, with the cabinet and port named.
  3. How long each step takes, so nobody panics at minute four.
  4. Who to call, and who signs that the line is back.

If the rollback needs the person who made the change, it is not a rollback.

Test it before the window

Walk the page with the shift lead a day early, on the real cabinet, with the power on and nothing touched. Every question they ask is a line missing from the page.