A rollback plan is read at the worst moment, by someone who did not write it. If it needs the engineer who made the change, it is not a plan.
We write every rollback for the operator on the night shift. One page, printed, and taped inside the cabinet door for the length of the window.
What goes on the page
- The one sign that tells you to roll back, in words the operator already uses.
- The steps, in the order the hands move, with the cabinet and port named.
- How long each step takes, so nobody panics at minute four.
- Who to call, and who signs that the line is back.
If the rollback needs the person who made the change, it is not a rollback.
Test it before the window
Walk the page with the shift lead a day early, on the real cabinet, with the power on and nothing touched. Every question they ask is a line missing from the page.