4 wind farms operating · 201 MW · 2,340 neighbours hold shares
Home / Company / How We Build
FILE WW-P04 · REV. 10/2026
[ Build programme ]

From first mast
to first power.

Eight years for Hartfell Edge, most of them spent listening. Five phases, four signed gates on site and a bulletin every Friday, so nobody has to guess what the trucks are for.

18-MONTH BUILD
41 PERMIT CONDITIONS
64 LOCAL HIRES
PROGRAMME FILE
WW-05 · 2026
18MONTHS
Hartfell Edge: first excavator in March 2026, first power due in Q3 2027.
FOUNDATIONS
20 / 20 poured
CABLE LAID
18.4 of 26 km
FIRST POWER
Q3 2027
 
ON THIS PAGE
01   Phases
02   Site gates
03   Programme
04   Turbine
01 / Phases

Five phases, and where you come in at each one.

Fifteen things you can read, check or question — each one published, each one with a date. If a date slips, the Friday bulletin says so the week it slips.

PHASE
WHAT WE DO
WHAT YOU SEE
HOW YOU TAKE PART
01
2 YEARS

Listen & measure

WHAT WE DO

A wind mast logs speed and direction for at least two years while we hold drop-in days and map every home within two miles.

WHAT YOU SEE
D1.1
Wind resource report
D1.2
Drop-in question log
D1.3
Home & distance map
HOW YOU TAKE PART

Come to a drop-in and tell us what worries you — every written question gets a written answer.

02
2 YEARS

Studies & layout

WHAT WE DO

Birds, bats, noise, flicker, landscape and water are studied in the field; the layout moves to meet what the studies find.

WHAT YOU SEE
D2.1
Six published studies
D2.2
Photomontages from your viewpoints
D2.3
Revised turbine layout
HOW YOU TAKE PART

Pick the viewpoints for the photomontages and comment on the draft layout.

03
1 YEAR

Permit & conditions

WHAT WE DO

We apply to the county, answer the hearing and agree the conditions: sound limits, flicker sensors, bat slow-downs, the fund and the discount.

WHAT YOU SEE
D3.1
County permit
D3.2
Signed permit conditions
D3.3
Share offer document
HOW YOU TAKE PART

Speak at the hearing, for or against, and register interest in shares if you want them.

04
18 MONTHS

Build

WHAT WE DO

Roads, foundations, cable and substation, then the turbine lifts. Blades travel by night convoy; local people are hired first.

WHAT YOU SEE
D4.1
Friday site bulletin
D4.2
Convoy timetable
D4.3
Local-hire report
HOW YOU TAKE PART

Sign up for the bulletin, and call the 24/7 site line if anything on the road goes wrong.

05
30 YEARS

Operate & give back

WHAT WE DO

Our control room runs the farm round the clock. Fund payments, bill credits and member interest start from first power.

WHAT YOU SEE
D5.1
Monthly output figures
D5.2
Yearly fund report
D5.3
Decommissioning bond in escrow
HOW YOU TAKE PART

Vote at the co-op AGM, sit on the fund panel — or just enjoy the lower bill.

02 / Site gates

Nothing on site moves on without a signature.

Four gates during the build, each with a short checklist and a named signatory — and the county inspector signs the first one with us.

G1
MONTH 8

Foundations signed off

Concrete tests on all 20 bases
Independent structural check
Spring and stream monitoring clean
SIGNED BY
Construction manager + county inspector
G2
MONTH 16

Grid energised

Substation tested by the utility
Protection settings approved
Cable route reinstated and seeded
SIGNED BY
Utility + head of wind resource
G3
MONTH 17

Turbines complete

Torque audit on every bolt row
Blade inspections signed
Flicker and bat sensors live
SIGNED BY
Turbine maker + site lead
G4
MONTH 18

First power

Sound checks at eight homes
Fund and bill credits switched on
Control room live for 7 days
SIGNED BY
Managing director + co-op board
PERMIT CONDITIONS TRACKED
41/ 41
LOCAL HIRES ON SITE
64/ 112
LOST-TIME INCIDENTS
02026
BLADE CONVOYS PLANNED
60by night
03 / Programme

Eighteen months of building, on one chart.

The grid connection is the one part we don’t control — so the utility’s substation work starts in month six, while the foundations are still curing. Updated in every Friday bulletin.

PHASE · DELIVERABLE
M0
M2
M4
M6
M8
M10
M12
M14
M16
M18
M20
M22
M24
01
Roads & site works
Tracks, crane pads, drainage
4 MOS
02
Foundations
20 bases, 620 m³ of concrete each
6 MOS
03
Grid connection
Substation, 26 km of cable
12 MOS · UTILITY-LED
12 MOS
04
Turbine lifts
Night convoys, two blades a week
5 MOS
05
Operate
Control room, fund, bill discount
30 YRS
Site gates
G1
G2
G3
G4
 
WESTERLY WORK
 
UTILITY / AUTHORITY TIMELINE
 
OPERATIONS
 
SIGNED SITE GATE
04 / Turbine datasheet

The machine on Hartfell Edge, and where the build stands.

Twenty identical turbines, chosen for slow-turning blades in low wind. The site bulletin on the right goes out every Friday to anyone who signs up.

Rated power 4.2 MW
SPEC
Cut-in 3 m/s, rated 11 m/s, cut-out 25 m/s · ≈ 12.9 GWh a year each.
Rotor 150 m · hub 112 m
SPEC
Tip height 187 m; the whole farm powers ≈ 24,000 homes.
≤ 35 dB(A) at the nearest home
LIMIT
A permit condition, checked with meters before and after.
94% recyclable by weight
END OF LIFE
30-year design life · $3.4M decommissioning bond in escrow.
SITE BULLETIN · WW-05
OCT 2026
Hartfell Edge — 20 × 4.2 MW
Phase 04 · Build · month 8 of 18
BUILD PROGRESS
45%
PROGRAMME
ON TRACK
FOUNDATIONS
20 / 20 poured
CABLE LAID
18.4 of 26 km
SAFETY
0 lost-time incidents
NEXT MONTH
Substation steel, tracks
Construction crew beside a freshly poured wind turbine foundation
PHOTO OF THE WEEK — base 14, the day after its 620 m³ pour
Next step / Come and ask

Questions about shares, sound or the fund? Ask the people who build the farms.

FREE · NO BOOKING · A REAL PERSON REPLIES IN TWO WORKING DAYS