Our largest farm yet: 84 MW on the Sable County ridge, 20% owned by the people who live around it. All 20 foundations are poured; turbines lift from Q2 2027 and first power follows in Q3.
Every figure comes from the permit, the turbine contract or the site log. Output is the P50 estimate from four years of mast data — the number the share offer is modelled on.

Most of the calendar was listening: drop-ins, studies and a permit with 41 conditions. Construction started in March 2026 and is on programme.