Thirteen turbines on four working farms in Owen County. The fields are still ploughed and grazed right up to the tower doors — the farms lost less than 1% of their land.
Figures from the as-built drawings and the export meter. Bracken Rise curtails at dusk in April–June under its bat permit, by design.

The build calendar was set by the four farms, not the other way round.
From April to June the turbines stop at dusk on low-wind nights, when bats feed. That shows in the spring bars — and is part of the plan.