The first question on a plant incident call is never about the network. It is about people and the process: is anyone at risk, and is the line safe?
Only then do we look at the screens. A contained network with a damaged process is a failure, whatever the report says.
The first ten minutes
- Is anyone at risk? Is the process in a safe state?
- What did the operator see, in their words?
- What changed in the last day: people, laptops, vendors, logic?
- What can we cut without stopping the line?
Keep the process safe first. The network can wait ten minutes.
Plan it before the night
Agree with operations which conduits can be cut at once, and which need their sign-off. Write it on the same page as the plant line number.