§1 Site sheetSR-188 / Sample figures

Sector | Pipelines, one gas transmission operator |
Scope | 6 stations, 1 control centre, 344 devices |
Findings | 2 High, 11 Low |
Windows | 9 used, all signed |
Result | Each station now its own zone |
Written for the plant manager: what we found on the floor, how the work ran, and what is different now.
Six compressor stations and one control centre shared a single flat network. A fault at one station could reach every other one, and the TSA Security Directives asked the operator to show a plan.
We listened for four weeks at the control centre and two stations, then drew one zone per station with one conduit back to the centre. Each station was cut over in its own window, with its crew on site.
Nine signed windows and no unplanned stop. Each station is now its own zone, and traffic between stations goes through the control centre or not at all.
§3 FindingsSR-188 / Sample figures

High | 2 | |
Low | 11 | |
Windows used | 9 |
Severity | Finding | Status |
High | One flat network across all six stations | Closed in W8 |
High | Vendor access straight into stations 2 and 5 | Closed in W9 |
Low | Station HMIs on an unsupported operating system | Shielded |
Low | No record of who changes compressor logic | Logged since W1 |
§4 Window logSR-188 / Sample figures
Copied from the site log. Every window had a date, a rollback and a signature before it opened.
When | Work | Signed by | Line |
Weeks 1 to 4 | Sensors at the control centre and stations 1 and 4 | Wardline | No outage |
Week 5 | Zone plan agreed, one zone per station | Control manager | No outage |
W1 | Control centre firewall, one conduit per station | Control manager | Signed window |
W2 | Station 1 cut over to its own zone | Control manager | Signed window |
W3 | Station 2 cut over to its own zone | Control manager | Signed window |
W4 | Station 3 cut over to its own zone | Control manager | Signed window |
W5 | Station 4 cut over to its own zone | Control manager | Signed window |
W6 | Station 5 cut over to its own zone | Control manager | Signed window |
W7 | Station 6 cut over to its own zone | Control manager | Signed window |
W8 | Old routes between stations removed | Control manager | Signed window |
W9 | Vendor access moved to the control centre gateway | Control manager | Signed window |
Afterwards | |||
Month 2 | Zone plan filed with the operator's security plan | Wardline | Filed |
Month 3 | First monthly monitoring report | Wardline | Monthly |
§5 Plant noteSR-188 / Sample figures
Every cut-over had the station crew on site and a rollback taped inside the cabinet. We never needed one.
One zone per station
One conduit per station, to the control centre
Vendor access only through the centre gateway
§6 More site reportsEnd of SR-188