The last of the twenty turbine foundations on Hartfell Edge was poured on 29 September, three weeks ahead of the programme we showed at the spring drop-in days. Each base is a circle of reinforced concrete 22 metres across, holding a steel anchor cage that the bottom tower section will bolt onto next spring.
One base, one day
A foundation has to be poured in one continuous session so the concrete cures as a single piece. That meant 620 m³ per base — about 78 truckloads — arriving at a steady rhythm from first light. We agreed the delivery windows with the county in 2023: no trucks through Sable village before 7:30, none during the school run, and a marshal at the Mill Road junction on every pour day.
What the numbers look like
- 20 of 20 foundations complete
- 18.4 of 26 km of buried cable laid
- 64 of 112 people on site from the three counties
- 0 lost-time incidents since March
Week by week from here
Over the winter the crews finish the cable trenches, build the crane pads and complete the substation building beside the Calder Ridge battery yard. Turbine components start arriving in April, with blades travelling at night in convoys of two. We will publish the full delivery calendar at least four weeks ahead, and the drop-in on 8 November at Norrow Grange Hall is the best place to ask about your road.
If you hold Hartfell Edge shares, nothing changes for you yet: interest starts in the spring after first power, which is still planned for the third quarter of 2027.