In 2024 we added a 20 MW / 40 MWh battery yard beside the Calder Ridge substation. It stores power when the wind is strong and demand is low, and releases it in the evening peak. This was its first full winter.

The headline numbers

  • 312 charge cycles between November and March
  • 94% of evening peaks covered on the target days
  • 99.1% availability across the season
  • 0 unplanned outages

The still week

Between 14 and 20 January the wind across all four operating farms fell below 4 metres per second for most of the week. The battery could not fill that gap on its own — no battery could — but it carried the evening peak on five of the seven nights by charging from the grid overnight.

Calder Ridge shareholders saw no change to their interest; the battery yard is owned by Westerly and pays its own way. A full report goes to the annual meeting in June.

Written By

Community Liaison
Community Liaison at Westerly. Lucia runs the drop-in days, keeps the site-line log and writes most of our field notes. She grew up in Larch Valley and has walked every Westerly ridge with the neighbours who live under it.
All notes by Lucia Ortega
More from the ridge

Three more field notes.

All News