4 wind farms operating · 201 MW · 2,340 neighbours hold shares

Night Convoys: Getting 60 Blades to Hartfell Edge

Each blade is 73 metres long. Here is the route, the timetable and how we keep the roads open by day.
A wind turbine blade on a long trailer travelling along a rural road at dusk

Next spring, 60 blades, 20 nacelles and 100 tower sections will travel from the port to Hartfell Edge. The blades are the hard part: each one is 73 metres long and rides on an extending trailer that needs the full width of the road on some bends.

Why at night

Moving blades between 22:00 and 05:00 keeps the county roads open for school buses, farm traffic and commuters. Two blades travel per night, with escort vehicles front and back and a police escort through the Sable junction.

The route

The convoy route was agreed with the county in 2024 after a trial run with a dummy load. Three passing places were widened and two road signs are folded down on convoy nights only; everything is put back after the last delivery.

The delivery calendar will be posted here and at every parish hall at least four weeks ahead. If you farm along the route and need to move stock at night, call the site line on +1-⁠555-⁠0165 and we will work around you.

Written By

Community Liaison
Community Liaison at Westerly. Lucia runs the drop-in days, keeps the site-line log and writes most of our field notes. She grew up in Larch Valley and has walked every Westerly ridge with the neighbours who live under it.
All notes by Lucia Ortega
More from the ridge

Three more field notes.

All News