On most of our projects the longest phase is not design or construction. It is the twelve weeks or more the utility needs to approve the connection. We cannot control that clock, but we can start it early and avoid restarting it.
Where the time goes
A 1 MWp application usually passes a completeness review, a screening study and, if the feeder is busy, a supplemental or full facilities study. Each stage can bounce back with questions, and each bounce adds weeks.
What shortens the wait
- A single-line diagram that matches the site exactly, signed by the engineer of record
- Twelve months of interval data so the utility can see the real export profile
- A clear statement of export limits or zero-export controls, if you will use them
Equipment lead times
Medium-voltage transformers and switchgear can take 30 to 50 weeks to arrive. We reserve production slots in week six of the programme, before final design, so the hardware is not the reason a finished array waits to switch on.
This is why our delivery programme files the interconnection application in week six, not after design is complete.