[ Project WW-08 · Scoping ]

Tamsin Flats,
just a mast for now.

A wind mast on the Owen County flats, measuring since March 2026. There is no layout yet — the first drop-in in spring 2027 comes before anything is drawn.

SCOPING
OWEN COUNTY
FIRST DROP-IN SPRING 2027
PROJECT FILE
WW-08 · REV. 10/26
40MW AT MOST
Up to 10 turbines, if the wind data and the first conversations support it.
WIND MAST
Up since Mar 2026
DATA SO FAR
7 months
FIRST DROP-IN
Spring 2027
 
ON THIS PAGE
01   What we know
02   Timeline
03   Neighbour voice
04   Gallery
01 / Spec sheet

What we know so far — and what we don’t.

Tamsin Flats is at the very start. These are the only facts on file; everything else will be decided with the people who live here.

Wind measurement mast on open moorland with a parked four-by-four
WW-08
SCOPING · SINCE MAR 2026
FIG. 01 — The Tamsin Flats wind mast, 100 m
PHOTO · APR 2026
FIG. 01 — The Tamsin Flats wind mast, 100 m
PHOTO · APR 2026
SCOPING FILE · TAMSIN FLATS
OCT 2026
CAPACITY
Up to 40 MW
TURBINES
Up to 10
WIND MAST
100 m · up since Mar 2026
DATA SO FAR
7 months
LAYOUT
None drawn yet
FIRST DROP-IN
Spring 2027
STAGE
Scoping
WHY HERE
Steady westerlies across flat, open farmland, a grid line within four miles and landowners who asked us to take a look.
WHAT WE’RE MEASURING
Wind speed and direction at four heights, temperature and icing — at least two years before any turbine is sized.
WHAT COMES FIRST
A drop-in before a drawing. We’ll show the wind data and ask what matters to you before a single turbine is placed.
02 / Timeline

At the very start of a long road.

If Tamsin Flats goes ahead, it follows the same order as every Westerly farm. Every date after 2026 is a plan.

2025
 
Landowner talks
Three farms on the flats invite us to measure the wind.
START
MAR 2026
 
Wind mast up
100 m mast installed; data shared with the landowners monthly.
NOW
2027
 
First drop-in
Wind data, constraints map and your questions — before any layout.
NEXT
2027–28
 
Studies
Birds, bats, noise, landscape, water and soils.
PLANNED
2029
 
Application
Only if the data and the conversations support it.
PLANNED
2031+
 
Share offer & build
Share offer first, construction after — as on every farm.
PLANNED
100M
Wind mast height
7MONTHS
Of wind data so far
3FARMS
Landowners on the flats
0TURBINES
Drawn so far — on purpose
03 / Landowner voice
“We asked them to measure, nothing more. They’ve shown us every month of data, and they’ve said plainly that if the village doesn’t want it, it doesn’t happen.”
TF
Tom Fenwick
ARABLE FARMER · TAMSIN FLATS
MAST DATA
MAR–SEP 2026
MEASURE
HEIGHT
SO FAR
Mean wind speed
100 m
7.9 m/s
Mean wind speed
60 m
7.1 m/s
Prevailing direction
100 m
WSW
Data recovery
All
99.2%
Seven months only — the summer half of the year. Not enough to size a farm.
MORE FROM THE REGISTER
Restored wildflower meadow with grazing cattle and wind turbines behind
PREVIOUS · WW-07

Norrow Hill

Planning · Larch County · 72 MW
Wind turbines on a misty green ridge at sunrise, with a battery yard beside the access road
NEXT · WW-01

Calder Ridge

Operating · Larch County · 48 MW
Next step / Live near Tamsin?

Hear about the first drop-in before anyone else.

FREE · NO BOOKING · A REAL PERSON REPLIES IN TWO WORKING DAYS