A temperature-controlled distribution hub under a 31,000 m² TPO roof. Our crews are installing a 1.6 MWp array on a 20-year PPA, on programme for energisation in Q4 2026 — and this page follows the same Friday report the client reads.
These figures come from the issued-for-construction drawings and the signed yield model. Year-one numbers replace them twelve months after energisation.

A cold store never really switches off: the night base sits near 60% of the peak. Grey is metered 2025 import; indigo is the signed model with the array running. We will publish the measured version after the first summer.
The standard programme from How We Deliver, with real dates. The interconnection application went in at week six, while design was still running.