Harbor Logistics
cut grid spend 31%.

A 26,000 m² distribution centre with cold docks running around the clock. We designed, built and now operate a 1.2 MWp roof array with 500 kWh of storage — on a 15-year PPA, with no capital from the client.

LOGISTICS
ASHFORD, TX
ENERGISED MAY 2025
PROJECT FILE
NB-0412 · REV. C
1.2MWp
Rooftop array plus a 500 kWh battery, energised 11 weeks after mobilisation.
CLIENT
Harbor Logistics Inc.
MODEL
15-yr PPA · $0.068/kWh
YEAR-ONE SAVING
$214,000
 
ON THIS PAGE
01   Spec sheet
02   Demand profile
03   Timeline
04   Gallery
01 / Spec sheet

One roof, one PPA, eleven weeks on site.

Every figure below comes from the as-built drawings and the first twelve months of revenue-meter data. Nothing is modelled unless it says so.

Distribution centre roof covered in solar modules above parked trucks
NB-0412
AS-BUILT · MAY 2025
FIG. 01 — 2,880 bifacial modules on a 26,000 m² TPO roof
DRONE SURVEY · JUN 2025
FIG. 01 — 2,880 bifacial modules on a 26,000 m² TPO roof
DRONE SURVEY · JUN 2025
SPEC SHEET · HARBOR LOGISTICS
REV. C
SITE
Ashford, TX · 26,000 m²
ROOF
TPO membrane · R-2
CAPACITY (DC / AC)
1.2 MWp / 1.0 MW
MODULES
2,880 × 420 W bifacial
INVERTERS
10 × 100 kW string
STORAGE
500 kWh / 250 kW LFP
ANNUAL YIELD
1,742 MWh P50 · 1,779 yr 1
SELF-CONSUMPTION
91%
CO₂ AVOIDED
679 t / year
COMMERCIAL MODEL
15-yr PPA, $0.068/kWh
ROOF TO ENERGISED
11 weeks
CHALLENGE
Afternoon cold-dock load drove a 1,840 kW peak and $28,600 a month in demand charges. The 2009 TPO roof was rated for 18 psf and nobody had checked the purlins.
ENGINEERING RESPONSE
We re-rated the roof, reinforced 14 purlin bays, then laid out 2,880 bifacial modules on low ballast. A 500 kWh battery is set to clip the 16:00–20:00 peak.
RESULT
Grid spend down 31% in year one, peak demand down 35%, and yield 2% above the P50 we signed for. The client paid nothing up front and buys power at a fixed rate.
02 / Demand profile

The afternoon peak, before and after.

Solar flattens the middle of the day; the battery takes the 16:00–20:00 shoulder when the docks are busiest and the sun is low. Same weekday, August 2024 versus August 2025.

GRID IMPORT · TYPICAL AUGUST WEEKDAY · kW
BEFORE
AFTER
 
500 kW
 
1,000 kW
 
1,500 kW
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
00:00
02:00
04:00
06:00
08:00
10:00
12:00
14:00
16:00
18:00
20:00
22:00
00
02
04
06
08
10
12
14
16
18
20
22
PEAK 1,840 → 1,190 kW
BATTERY 16:00–20:00
SOLAR 08:00–17:00
AUGUST BILL
2024 VS 2025
LINE
BEFORE
AFTER
Energy charges
$61,400
$38,900
Demand charges
$28,600
$18,500
Fixed & riders
$4,100
$4,100
Total
$94,100
$61,500
−35%
PEAK DEMAND
−31%
GRID SPEND, YEAR ONE
03 / Timeline

Sixteen months from first call to first kWh.

Most of the calendar was paperwork: the utility study and the PPA. On the roof itself, one crew worked eleven weeks around live loading docks.

JAN 2024
 
Feasibility study
12 months of interval data, a roof survey and three priced options in ten working days.
PHASE 01
MAR 2024
 
PPA signed
15-year agreement at $0.068/kWh, fixed, with a yield guarantee at P50.
PHASE 02
SEP 2024
 
Grid approval
Utility study cleared with no upgrade cost after we capped export at 600 kW.
PHASE 03
FEB 2025
 
Mobilised
Purlin reinforcement first, then racking — the docks never closed.
PHASE 04
MAY 2025
 
Energised
Commissioned and witnessed by the utility, 11 weeks after mobilisation.
LIVE
MAY 2026
 
Year-one report
Yield at 102% of P50, availability 99.6%, grid spend down 31%.
O&M
11WEEKS
Mobilisation to energised
0LTI
Lost-time incidents, 21,400 hours
0CLOSURES
Dock closures during build
14BAYS
Purlin bays reinforced
05 / Client voice
“Our board signed a PPA because Northbeam showed us the load data first. A year later the bill matches their model within three per cent — and nobody on the dock floor noticed the build.”
DM
Dana Mercer
VP FACILITIES · HARBOR LOGISTICS INC.
YEAR ONE VS MODEL
MAY 2026
METRIC
MODEL
ACTUAL
Annual yield
1,742
1,779 MWh
Self-consumption
88%
91%
Grid spend
−28%
−31%
Availability
99.0%
99.6%
Weather-corrected. Independent review by the client’s energy consultant, June 2026.
MORE FROM THE REGISTER
Solar carport canopies over a staff car park with EV chargers
PREVIOUS · NB-0398

Ashford Civic Solar Canopy

Campuses · 310 kWp
Warehouse interior with racking, a forklift and pallets of solar modules
NEXT · NB-0431

Tamsin Cold Chain

Logistics · 1.6 MWp · in build
Next step / Feasibility study

Send 12 months of bills. Get three priced options in 10 working days.

NO FEE · NO OBLIGATION · AN ENGINEER REPLIES IN ONE WORKING DAY
DIRECT LINES
SALES DESK
+1-555-0188
O&M DESK
24 / 7 / 365