A regional distribution centre whose electric delivery vans all charge before the morning routes. We built a 520 kWp array on its standing-seam roof without a single penetration, plus a 400 kWh battery that takes the early charging peak.
As-built figures and the first twelve months of meter and battery data. The clamp detail was approved by the roof manufacturer before a single module arrived.

The worst quarter-hour of the day comes before sunrise, when the whole fleet is plugged in. The battery covers it from solar stored the afternoon before. Same June weekday, 2022 versus 2023.
The longest single task was not the build but the clamp approval: the roof manufacturer tested our detail on a sample panel before signing.