A two-shift machining plant with 2.6 hectares of empty land beside the factory. We built a 1.6 MWp single-axis tracker field and tied it in at medium voltage — behind the meter, with every kWh bought under a 20-year PPA.
As-built drawings and the first twelve months of revenue-meter data. The tracker gain is measured against a fixed-tilt reference string on the same site.

A tracker field keeps producing late into the afternoon, when the second shift is at full load. Same July weekday, 2024 before energisation versus 2025.
A ground-mount needs a land-use permit and a grid study, so the paperwork ran longer than the build. On site, piling to energised took thirteen weeks.